Outside 3 Amersham Hill Gardens, HP13 6QP
Reported via desktop in the Failed reinstatement category anonymously at 13:30, Thu 30 May 2024
Sent to Buckinghamshire Council 6 days, 3 hours, 51 minutes later. FixMyStreet ref: 6039405.
SSE repaired the street light which includes underground work. They made good the pavement. They left behind a shuttering board on the road. This board is now breaking up. Action required: Clean the street and place the cost and fine SSE for not doing / completing their job properly.
Updates
-
This has been passed to our Street Scene Team who will carry out an inspection of the area and arrange for the appropriate action to be taken.
Posted by Buckinghamshire Council at 13:30, Thu 30 May 2024
-
State changed to: Investigating
Updated by Buckinghamshire Council at 13:40, Thu 30 May 2024
-
State changed to: For Triage
Updated by Buckinghamshire Council at 09:50, Mon 3 June 2024
-
After carrying out any work on the highway, this includes the footpaths/verge, companies who have a legal right or permission to work on the public highway must adhere to the standard set out in the Code of Practice for Reinstatements. These works are guaranteed for 2-3 years dependant on the depth of excavation, if a reinstatement fails and is within the guarantee period, we can instruct them to fix the fault.
We as the Highway Authority will always carry out an inspection on these reinstatements and if they are deemed to be below standard we will instruction the company to come back out and resolve at their costs, not the taxpayer.
State changed to: Open
Posted by Buckinghamshire Council at 17:21, Wed 5 June 2024
This report is now closed to updates from the public. You can make a new report in the same location.