Incorrect road closure date

Reported via desktop in the Missing roadworks on one.network category anonymously at 11:53, Thu 9 May 2024

Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 5950689.

There is a Preston Hill road closure on 21st May which One.Network states as a 1 day closure for Remedial works. The letter which has been received by residents states the closure will be Mon-Fri. Are the dates on the letter an error? Please can this be confirmed? Thank you. Permit ref: D400200044714-02

Updates

  • All planned work on the public highway (this includes the footpath) in Buckinghamshire, must apply for a permit from us as the local Highway Authority prior to any work starting.

    However, there are occasions when work starts before a permit is issued for example emergency work such as a gas leak. The Utility company can start work which is why some are not shown on One.Network, but they must advise us within 2 hours of the start of the works. We will then ensure the works are added to the system.

    A Highways Inspector will attend the site and/or contact the relevant Utility Company to ensure the conditions of the road permit licence are met.