Kerbline opposite traffic signal island

Reported via desktop in the Kerb damage / issue category anonymously at 10:42, Tue 9 April 2024

Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 5827950.

The metal kerb weir unit next to the gully has broken in two, one piece has been dislodged and is now in the channel line

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • The report has been passed to the Highway Officer, who will carry out an inspection of the issue within 10 working days, emergency defects will be corrected or made safe at the time of the inspection, if reasonably practicable to do so. In this context, making safe may constitute displaying warning notices, coning‐off or fencing‐off to protect the public from the defect or other suitable action. If the inspection team cannot make safe the defect at the time of inspection, then they will instigate the relevant emergency call procedures to ensure appropriate resources are mobilised to make the defect safe.

    There may also be occasions when the issue reported will not be repaired as it has been classified as a minor defect and does not pose any risk to either the safety or the integrity of the highway, these are called minimum recording levels as specified in our Highways Safety Inspection Policy.

    Posted by Buckinghamshire Council at 10:42, Tue 9 April 2024

  • Update

    The Highway Officer has carried out an inspection and has identified that there is no immediate safety issues requiring attention, the decision is that no action will be taken at this stage.

    The issue will be added to a package of works to be carried out at a later date.

    Please note that all our roads are subject to regular Highways Safety Inspections, and all highway safety issues identified are actioned within the timescales set out in our policy.

    State changed to: Closed

    Posted by Buckinghamshire Council at 12:37, Tue 23 April 2024