Most of footpath blocked

Reported via desktop in the Footpath / pavement problem category anonymously at 08:54, Wednesday 28 February 2024

Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 5642448.

Along this section of footpath there are two sections where the footpath is half blocked by very deep mud. This is the only route in and out of Lent Rise school for people using the top gate and as there is no safe place to cross all the parents and children need to walk in this section and it is now impossible for people to pass each other. The mud and grass all needs pushing back urgently to reveal the whole footpath again.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • The report has been passed to the Highway Officer, who will carry out an inspection of the issue within 10 working days, emergency defects will be corrected or made safe at the time of the inspection, if reasonably practicable to do so. In this context, making safe may constitute displaying warning notices, coning‐off or fencing‐off to protect the public from the defect or other suitable action. If the inspection team cannot make safe the defect at the time of inspection, then they will instigate the relevant emergency call procedures to ensure appropriate resources are mobilised to make the defect safe.

    There may also be occasions when the issue reported will not be repaired as it has been classified as a minor defect and does not pose any risk to either the safety or the integrity of the highway, these are called minimum recording levels as specified in our Highways Safety Inspection Policy.

    Posted by Buckinghamshire Council at 08:55, Wednesday 28 February 2024

  • Update

    The Highway Officer has attended the site and carried an inspection based on your report.

    We assess repairs in accordance with our Highways Safety Inspection Policy. This allows us to prioritise the most serious repairs to be completed urgently, with more minor defects such as this one being planned to be completed within 6-8 weeks.

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:42, Tuesday 12 March 2024

This report is now closed to updates from the public. You can make a new report in the same location.