Woodways
Reported via desktop in the Road surface category by Haddenham Parish Council at 11:34, Mon 21 February 2022
Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 3330373.
Collapsed drain
Updates
-
Thank you for your report which is currently under review.
We will investigate this will respond to you within 10 working days.IMPORTANT: If you consider this to be dangerous or an emergency, please call us on 0300 131 6000
Otherwise, by submitting the report online we will deal with it in line with our agreed timescales.Regards
Buckinghamshire CouncilPosted by Buckinghamshire Council at 11:34, Mon 21 February 2022
-
Thank you for your report.
We have inspected the defect and will aim to repair within 6-8 weeks.We will continue to monitor this in line with our Highways Safety Inspection Policy.
Feedback helps us improve our services, so please tell us your views using this simple Form..
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:40, Tue 1 March 2022
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:40, Tue 1 March 2022
-
Thank you for your report.
We have inspected the defect and will aim to repair within 6-8 weeks.We will continue to monitor this in line with our Highways Safety Inspection Policy.
Feedback helps us improve our services, so please tell us your views using this simple Form..
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:40, Tue 1 March 2022
-
State changed to: In progress
Updated by Buckinghamshire Council at 11:06, Tue 1 March 2022
This report is now closed to updates. You can make a new report in the same location.