report here Reposition
report here
Fixed
O/s house named Dalbrae in Aylesbury Road for next 50 metres towards Princes Risborough
Reported via desktop in the Footpath / pavement problem category anonymously at 11:12, Mon 4 October 2021
Sent to Buckinghamshire Council less than a minute later
The attached photographs indicate the poor state of the footway. On Tuesday 21st September at approximately 3.35pm my wife was walking our grand daughter home from Monks Risborough School towards Princes Risborough when she fell having trodden on an uneven section of pavement (See Photographs). Having attended the A&E at Stoke Mandeville Hospital it was established that she had two fractures to her right foot and severe bruising (See Photograph). She now has to wear a surgical boot for 8 weeks. I understand that the poor condition of this footway has been reported to you a number of times. Please rectify the problem before any further incidents occur resulting in a more serious injury.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:13, Mon 4 October 2021
-
Thank you for your report.
An initial assessment has been made and further work to investigate your enquiry is required. This should be completed within the next 10 days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:51, Mon 11 October 2021
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:35, Thu 14 October 2021
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:35, Thu 14 October 2021
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:38, Thu 14 October 2021
-
State changed to: In progress
Updated by Buckinghamshire Council at 12:20, Thu 14 October 2021
-
Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 13:33, Tue 19 October 2021
-
We are pleased to tell you that the repair of this defect is now complete.
Please consider completing our short survey below on how you found the repair;
https://forms.gle/ FywWv2ZGrGb9XgCu8The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 13:34, Tue 19 October 2021
This report is now closed to updates. You can make a new report in the same location.