Many potholes all along this stretch

Reported via mobile in the Pothole category by J Rennard at 04:18, Wed 22 September 2021

Sent to Buckinghamshire Council less than a minute later

Buses, lorries and school traffic have to dodge the potholes along a narrow stretch of road thus putting oncoming traffic at risk during busy periods. This has been a problem for years with superficial repairs sometimes only lasting hours before reappearing. Attempts to repair these holes have been poor quality workmanship and rarely tackle the root of the issue. It's time Jason's Hill residents' reports of potholes are taken seriously and repaired properly and not dismissed.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 04:18, Wed 22 September 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 14:08, Wed 6 October 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 14:08, Wed 6 October 2021

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 14:08, Wed 6 October 2021

  • State changed to: In progress

    Updated by Buckinghamshire Council at 13:16, Thu 7 October 2021

  • Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 15:07, Wed 13 October 2021

  • We are pleased to tell you that the repair of this defect is now complete.

    Please consider completing our short survey below on how you found the repair;
    https://forms.gle/ FywWv2ZGrGb9XgCu8

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway.

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 15:23, Wed 13 October 2021

This report is now closed to updates. You can make a new report in the same location.