report here Reposition
report here
Fixed
Opposite Haddenham Carpets
Reported via desktop in the Pothole category anonymously at 17:57, Mon 23 November 2020
Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 2402061.
Large oval pothole in the kerb opposite Haddenham Carpet shop on the church side of Willis Rd. Other potholes and road damage have been marked outside Ivor Miles garage but not this one. Full of water but looked deep. At least 12 inches by 18
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 17:57, Mon 23 November 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:10, Wed 25 November 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:10, Wed 25 November 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 09:10, Wed 25 November 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 09:29, Wed 25 November 2020
-
Thank you for your report; we are pleased to advise that the repair of this defect is now in progress. We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 08:25, Wed 2 December 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 09:08, Wed 2 December 2020
This report is now closed to updates. You can make a new report in the same location.