Blocked Drain

Reported in the Blocked drain category anonymously at 18:32, Thu 13 August 2020

Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 2244279.

Hello there, The drain which abuts our property floods with every downpour of rain, causing flooding to both the public footpath and our drive (Leaside, Cryers Hill Lane), I wonder if perhaps you could arrange for the drain to be cleared?

With thanks, Peter

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report which is currently under review.
    We will investigate this and if you have provided an email address, we respond to you within 10 working days.
    We will continue to update you by email (if provided) when your report reaches key stages.
    IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
    Regards
    Transport for Buckinghamshire

    Posted by Buckinghamshire Council at 18:32, Thu 13 August 2020

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:01, Tue 18 August 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 11:01, Tue 18 August 2020

  • Thank you for your report.
    We have completed our inspection of the defect, which we aim to repair within five working days.
    We will continue to update you by email when your report reaches key stages.
    Regards
    Transport for Buckinghamshire

    State changed to: Action scheduled

    Posted by Buckinghamshire Council at 11:01, Tue 18 August 2020

  • State changed to: In progress

    Updated by Buckinghamshire Council at 08:21, Wed 19 August 2020

  • We are pleased to tell you that the repair of this defect is now complete.

    The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway

    Regards
    Transport for Buckinghamshire

    State changed to: Fixed

    Posted by Buckinghamshire Council at 09:06, Mon 24 August 2020

This report is now closed to updates. You can make a new report in the same location.