report here Reposition
report here
Fixed
68 New Road
Reported in the Footpath / pavement problem category anonymously at 12:14, Mon 20 July 2020
Sent to Buckinghamshire Council less than a minute later. FixMyStreet ref: 2208318.
Damaged footpath, concrete is raised approximately 6 inches and dangerous, in addition the tarmac to the left of the concrete damage, if you are looking at the property is swollen/raised and a potential trip hazard. We are struggling to get out of our drive due to the raised concrete. We noticed this damage occurred sometime last week.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 12:15, Mon 20 July 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within two working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:22, Tue 21 July 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 10:22, Tue 21 July 2020
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within two working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:23, Tue 21 July 2020
-
State changed to: In progress
Updated by Buckinghamshire Council at 13:47, Tue 21 July 2020
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 11:14, Thu 23 July 2020
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 11:26, Thu 23 July 2020
This report is now closed to updates. You can make a new report in the same location.