On the exit of the village on the lefhandside, as you travel towards Cuddington
Reported in the Pothole category anonymously at 13:21, Sun 31 March 2019
Sent to Buckinghamshire Council 3 minutes later
This pothole is on the bend just as you exit the village road onto Cannons Hill towards Cuddington. It is causing drivers to move towards the middle of the road into the path of oncoming traffic. It is particularly dangerous as cars turning into the village do so at speed (existing a 60 mph road) so there is a high possibility of a collision with a car avoiding the pothole.
Updates
-
Thank you for your report which is currently under review.
We will investigate this and if you have provided an email address, we respond to you within 10 working days.
We will continue to update you by email (if provided) when your report reaches key stages.
IMPORTANT: To report anything dangerous, please call us on: 01296 382416 (09:00 – 17:30 Mon-Thurs, 09:00 – 17:00 Friday) or 01296 486630 (out of hours and weekends).
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 13:25, Sun 31 March 2019
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:20, Mon 1 April 2019
-
State changed to: In progress
Updated by Buckinghamshire Council at 10:20, Mon 1 April 2019
-
Thank you for your report.
We have completed our inspection of the defect, which we aim to repair within five working days.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for Buckinghamshire
State changed to: Action scheduled
Posted by Buckinghamshire Council at 10:48, Mon 1 April 2019
-
State changed to: In progress
Updated by Buckinghamshire Council at 12:26, Mon 1 April 2019
-
Thank you for your report, the repair of this defect is now in progress.
We will continue to update you by email when your report reaches key stages.
Regards
Transport for BuckinghamshirePosted by Buckinghamshire Council at 12:11, Tue 2 April 2019
-
We are pleased to tell you that the repair of this defect is now complete.
The reports you make to us are invaluable, they help us achieve our pledge to always put safety first by prioritising the most critical repairs, being available to react 24/7 and regularly inspecting the highway
Regards
Transport for Buckinghamshire
State changed to: Fixed
Posted by Buckinghamshire Council at 12:11, Tue 2 April 2019
This report is now closed to updates. You can make a new report in the same location.